"NASA's Mars Science Laboratory Project continues to press ahead with launch preparation activities, planning to use additional time before encapsulating the rover in the launch vehicle's nose cone.

Officials want to maintain additional schedule margin for enhanced safety procedures in assembly and testing. System testing put the rover and other parts of the spacecraft through simulations of many activities from launch through operations on Mars' surface. Aspects of the test simulating the final moments before landing took longer than scheduled. Additional margin that had been built into the schedule has been consumed in recent weeks by stepped-up safety procedures in assembly and testing."